It was week 6 when we saw the progress of our home improvement. In my Home Improvement week 4, I have mentioned that the stairs were built and the concrete slab is dry already. There was a delay in week 5 because our contractor had stopped working due to barangay clearance working permit issue but it was resolved already. When we got the construction bond, we were not informed that our workers or contractor need the barangay clearance working permit which is also a requirement in the home … [Read more...] about Home Improvement at Las Palmas week 6